A project starts out as which of the following?


A) A statement of work
B) Critical path method (CPM)
C) A series of milestones
D) A Gantt chart
E) A latest-start-time estimate

F) A) and E)
G) A) and D)

Correct Answer

verifed

verified

What is that sequence of activities that consume the longest amount of time in a project network of activities called? _______________________________

Correct Answer

verifed

verified

the critical path
Explanation:...

View Answer

What do the initials EVM stand for? _______________________________________

Correct Answer

verifed

verified

earned value managem...

View Answer

Complex projects are often subdivided into a series of tasks that are typically configured to be not longer than several months in duration.

A) True
B) False

Correct Answer

verifed

verified

A project may be defined as a series of related jobs directed toward some major output and requiring a significant period of time to perform.

A) True
B) False

Correct Answer

verifed

verified

For an activity in a CPM analysis, the early finish time is 20 and the late finish time is 20.Which of the following statements is true?


A) The activity's late start must happen before its early start.
B) The activity is on the critical path.
C) The slack for this activity is 20.
D) The duration of this task is zero.
E) The duration of this task is 20.

F) A) and D)
G) C) and D)

Correct Answer

verifed

verified

The activity direct costs associated with a project might include giving workers overtime to complete a project in less than the expected time.

A) True
B) False

Correct Answer

verifed

verified

True

You have collected the data for a time-cost CPM scheduling model analysis.The time is in days and the project "direct costs" are given here. You have collected the data for a time-cost CPM scheduling model analysis.The time is in days and the project  direct costs  are given here.   The indirect costs for the project are determined on a daily duration basis.If the project lasts 16 days, the total indirect costs are $400; 15 days, they will be $250; 14 days, they will be $200; and 13 days, they will be $100.If you crash this project by one day what is the total (i.e., direct and indirect) project cost? ____________________  E.A costs $100/day to crash, D costs $150/day to crash, and E costs $400/day to crash.Reducing the duration of A by one day at an additional cost of $100 is the most economical.Direct costs are now $400 + $100 + $200 + $400 + $500 + $200 + $100 = $1,900.Overall duration of the project is 15 days, and indirect costs are $250.The total cost of crashing this project for one day is $2,150. The indirect costs for the project are determined on a daily duration basis.If the project lasts 16 days, the total indirect costs are $400; 15 days, they will be $250; 14 days, they will be $200; and 13 days, they will be $100.If you crash this project by one day what is the total (i.e., direct and indirect) project cost? ____________________ E.A costs $100/day to crash, D costs $150/day to crash, and E costs $400/day to crash.Reducing the duration of A by one day at an additional cost of $100 is the most economical.Direct costs are now $400 + $100 + $200 + $400 + $500 + $200 + $100 = $1,900.Overall duration of the project is 15 days, and indirect costs are $250.The total cost of crashing this project for one day is $2,150.

Correct Answer

verifed

verified

$2,150
Explanation: The critical path is...

View Answer

Here are the data for a time-cost CPM scheduling model analysis.The time is in days and the costs include both direct and indirect costs. Here are the data for a time-cost CPM scheduling model analysis.The time is in days and the costs include both direct and indirect costs.   What are the total time of this project and total normal cost? A) Total time is 13 days, total cost is $1,200. B) Total time is 12 days, total cost is $1,700. C) Total time is 11 days, total cost is $1,600. D) Total time is 10 days, total cost is $1,750. E) Total time is 9 days, total cost is $1,700. What are the total time of this project and total normal cost?


A) Total time is 13 days, total cost is $1,200.
B) Total time is 12 days, total cost is $1,700.
C) Total time is 11 days, total cost is $1,600.
D) Total time is 10 days, total cost is $1,750.
E) Total time is 9 days, total cost is $1,700.

F) A) and E)
G) A) and C)

Correct Answer

verifed

verified

The second step in managing a project is writing the statement of work.

A) True
B) False

Correct Answer

verifed

verified

What is a work breakdown structure?


A) A list of the activities making up the higher levels of the project
B) A definition of the hierarchy of project tasks, subtasks, and work packages
C) A depiction of the activities making up a project
D) A Gantt chart
E) A structure that is incompatible with the critical path method

F) None of the above
G) B) and D)

Correct Answer

verifed

verified

In CPM analysis, it is generally expected that the relationship between activity direct costs and project indirect costs will be which of the following?


A) Positively related
B) Optimally related
C) Negatively related
D) Not related
E) Fractionally related

F) None of the above
G) A) and E)

Correct Answer

verifed

verified

You have been placed in charge of a large project.Shortened communication lines are required to ensure quick resolution of problems as they arise.You recognize that the project is going to take a lot of time and require a lot of team pride, motivation, and commitment by all members.Which project management structure should you use in this situation?


A) Pure project
B) Task force
C) Matrix project
D) Functional project
E) PERT

F) None of the above
G) A) and E)

Correct Answer

verifed

verified

Project management can be defined as planning, directing, and controlling resources to meet the technical, cost, and time constraints of the project.

A) True
B) False

Correct Answer

verifed

verified

True

A series of projects that are organized in such a way that each project utilizes people from different functional areas is using which of the following organizational structures?


A) Matrix project
B) Integrated task force
C) Functional project
D) Pure project
E) Cross-functional flexible team

F) A) and C)
G) A) and E)

Correct Answer

verifed

verified

You are managing a project and need to cut the cost of the project.You decide to transfer workers to another job to cut the project's costs.Costs associated with transferring the workers are an example of project indirect costs.

A) True
B) False

Correct Answer

verifed

verified

When reducing the planned duration of a project using the time-cost CPM model, we select the activity to crash by determining the cost of each alternative and selecting the one whose cost is the greatest.

A) True
B) False

Correct Answer

verifed

verified

Popular project management software used in mid-sized projects is


A) Microsoft Word.
B) Microsoft Primavera.
C) Microsoft Project.
D) Microsoft Excel.
E) None of these

F) C) and E)
G) C) and D)

Correct Answer

verifed

verified

Here are the data for a time-cost CPM scheduling model analysis.The time is in days and the costs include both direct and indirect costs. Here are the data for a time-cost CPM scheduling model analysis.The time is in days and the costs include both direct and indirect costs.   If you crash this project to reduce the total time by one day, what is the total time of the project and total cost? A) Total time is 13 days, total cost is $1,500. B) Total time is 12 days, total cost is $2,000. C) Total time is 12 days, total cost is $2,300. D) Total time is 11 days, total cost is $1,850. E) Total time is 11 days, total cost is $2,350. If you crash this project to reduce the total time by one day, what is the total time of the project and total cost?


A) Total time is 13 days, total cost is $1,500.
B) Total time is 12 days, total cost is $2,000.
C) Total time is 12 days, total cost is $2,300.
D) Total time is 11 days, total cost is $1,850.
E) Total time is 11 days, total cost is $2,350.

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

D

A disadvantage of a matrix project organizational structure is that a project manager is held responsible for successful completion of the project.

A) True
B) False

Correct Answer

verifed

verified

Showing 1 - 20 of 78